Day #122 and another check

so derek asked me to meet with EZ today to give him the next check for $10k and to ask him some questions. apparently next week (or the next, depending) they will be awaiting 4 rough inspections, on: electrical, plumbing, hvac, and framing. after that will come the need for 4 more checks too. then after those are done, they can start to install the roof.
EZ said that in the meantime, they are able to put the (black) paper over the plywood on the outside walls, and then the wire mesh afterwards (which were still waiting to be done when i was there) to prepare for the stucco. they can't put the stucco on just yet, but they were given the ok to prepare for it.



Wednesday, February 27, 2008

Sunday, February 24, 2008

Day #117

some trenches in the front yard. new sewage lines?
the ficus tree blocking the sliding glass door is finally gone
another closet downstairs, now that the heater won't be in it.
a view out mom's bedroom
our corner shower in our bathroom
the mostly fixed closet in the family room

Tuesday, February 19, 2008

Sunday, February 17, 2008

Day #110

derek and i stopped by before our sunday morning grocery run to see what had been done yesterday. guess they finally put in the sliding glass door by mom's room. but derek's still got to take that ficus tree down that's in the way.
the back of the house
pipes in our bathroom
a circuit breaker in the hallway upstairs

Friday, February 15, 2008

Thursday, February 14, 2008

Day #108

[photos courtesy of matthew]
a guy working on the awning? i didn't remember if we had one...
from the downstairs bedroom through the closet, to the stairs
window in the kitchen area
saw some pipes in the master bath